Work Order Operation Plan

Defines operation level status of work orders listed in work order plan. It provides information like quantities in various states, operation start and end times etc. This is generated based on operation resource during the creation of work orders.

Creating a Work Order Operation Plan

Field Description.
WorkOrderId This is a unique identifier used to track work orders. These columns cannot be modified.
RoutingId Routing used by this work order. These columns cannot be modified
Operation This identifies the operation. These columns cannot be modified
ResourceId Resource assigned for this work order
OperationSeq Sequence of this operation. These columns cannot be modified
JobStatus Status of this operation whether it is pending, started or completed
QtyPlanned This is the quantity of items planned by this work order on this operation. This is the produced quantity after the yield calculation. These columns cannot be modified
QtyCompleted The total number of units completed at this operation for this work order. This is a cumulative value for the job.
QtyRejected The total number of units rejected at this operation for this work order.
PlannedStartTime Planned start time of this work order for this operation. This is populated only if the work order is scheduled. These columns cannot be modified directly.
PlannedEndTime Planned start time of this work order for this operation. This is populated only if the work order is scheduled. These columns cannot be modified directly.
ActualStartTime Actual start time of this work order for this operation. They can be entered directly.
ActualEndTime Actual end time of this work order for this operation. They can be entered directly.
LPST Latest possible start time of the order at this operation. If the order goes beyond LPST, it means that the order will be late. These columns cannot be modified directly.
EPST Earliest possible start time of the order at this operation. Order cannot be made earlier than this date due to material availability constraints. These columns cannot be modified directly.
BucketDate Date on which operation should start. These columns cannot be modified
EndBucketDate Date on which operation gets completed
ActualDuration This is the actual total time taken to complete this operation. This is used for actual cost calculation.
Remarks While making any changes to the work order, the user can specify the reason for the changes.

img

Validation

  • WorkOrderId, operation and resource id combination should be unique.

  • QtyCompleted should be less than or equal to QtyPlanned

Changing to Alternate Resource

There could be a situation when

  • Work order has to be split and loaded both in primary and alternate resource

  • Work order which is loaded both in primary and alternate to be merged to one resource

In order to do the above, do the following

  • Select one of the rows from the work order operation plan

  • Click on the Split/Merge button

  • A new window will pop up

  • Add a new row if the work order has to be split by adding Resource, Quantity and Bucket Date

  • If zero is entered as quantity, then the work order on that resource will be removed